Esk Landfill Cell 4 Construction
Projects
Location: Esk
Value: $2.6M
Client: Somerset Regional Council
Duration: September 2021 – March 2022
Description:
Landfill – Cell Construction
100,000 m3 of excavation through rock and clay
Scope:
Construction of Cell 4 including –
Bulk Excavation, Detailed Excavation, Embankment and Clay Lining, Geomembrane Constructions, Detailed Management of Contaminated Material, Erosion and Sediment management including Environmental Management.
Challenges:
Wet Weather, Non-Rippable rock in excavation, Bulk Material Storage (minimal available area), Environmental sensitive receptors.